OVM Seismic Isolation and Vibration Damping Technology provides technical support for the Xinjiang Naba Expressway

 

Deep in the Tianshan Mountains, the construction of Xinjiang's key transportation project, the G218 Narati to Barentai Expressway, is progressing vigorously. The constructors are seizing the golden construction period, promoting the construction of high-quality projects and ensuring the early completion of the road.

 

The Naba Highway links the towns of Narathi and Barentai, with a total length of 217.6 kilometers. The proportion of bridges and tunnels in the project is high, the scale of bridge and tunnel construction is large, the population along the line is sparse, and it is located in the area of extreme cold, high altitude, high latitude and high earthquake intensity.The seismic isolation of highway bridge superstructure is particularly important.

 

The NBTZ-8 section of Naba Expressway, constructed by Shanxi Road and Bridge Construction Group, has a total length of over 30 km and comprises several bridges. Among them, 40 meters of prefabricated T-beams constitute an important part of this section. These T-beams will be erected on HDR(I) high-damping isolation bearings produced by OVM. When an earthquake occurs, the high damping isolation bearing absorbs and dissipates seismic energy through its own deformation, thereby reducing the seismic force transmitted to the superstructure and enhancing the overall seismic performance of the bridge.

 

The HDR(I) High damping isolation bearings developed and produced by Liuzhou Orient engineering rubber products co.,ltd of OVM are a device employed in bridges and building structures to mitigate the structural damage caused by earthquakes. By setting a high damping rubber isolation layer at a specific part of the structure, it can extend the natural vibration period of the structure and reduce the response under earthquake action, thereby protecting the main body of the structure from incurring or only incurring minor damage.

The high-damping isolation bearings worth more than 10 million yuan provided by OVM for the NBTZ-8 section of Naba Expressway,possess excellent bearing capacity, good stability, resetting function and anti-torsional ability, and are widely utilized in practical projects such as bridges and buildings. To guarantee the quality of the project, these bearings are tested in accordance with the corresponding technical specifications, including bearings material testing and finished bearings testing, to ensure that the vertical bearing capacity, compression performance and horizontal performance indicators all meet the requirements.

After the completion of Naba Highway, it will become a convenient channel for communicating the Ili River Valley region and Korla in southern Xinjiang, which can significantly shorten the distance between the regions and save travel time. By then, the drive from Barentai to Narati will be reduced to two hours. It holds great strategic significance in realizing the "inner circle of Xinjiang, faster entry and exit of Xinjiang" and promoting tourism and economic development along the line.